Sunday, 26 July 2015

Friends in Blue

Sometimes friends come out, even when it's raining!

 Five of the six wall pieces are done, and I'm eager to see them raised!

 Three pieces up!  Wow, it's taller than I expected!  :)

Five pieces up.  Used palette wrap and tarps to keep the rain out.   Until next time!

Friday, 24 July 2015

Alone in the Rain

Some days it rains...



...and tarps leak.


Some days it's just me...


...working inside, out of the rain.



Sunday, 12 July 2015

Filming & Wall Framing: Part 2

Today was full of excitement, as we had filmmakers come to document the building process!

 Claire, Chuck, Kevin and Joshua - the talented crew!

  Claire on camera.

 
 Kevin with his boom mic.

While I reviewed the plans for the third wall.

 There were time consuming notches to be made in the studs...

 ...but these ladies made it look easy.

Fits like a glove!


Progress was slow today, but we ALMOST got the third piece of wall finished. The angles and notching slowed us down, but mostly is was my lack of confidence leading to long periods of indecision.  Next time, I'm just gonna go for it!  All this time spent hemming and hawing over the right way to proceed gets me nowhere.  Instead of overthinking, trying to foresee all the issues, time would be better spent just doing it, and dealing with the issues as they arise.  At least, that's what I'll try next time.  :)

Saturday, 11 July 2015

Wall Framing: Part 1

Now the fun begins, framing the walls!  Big thanks to Beth, Jared and Kyle for coming out for day one of framing!








 Wall # 1 done!  A milestone! :)

And wall #2 well on it's way!

We may have gotten more done if it wasn't such a lovely day, but the lake was calling to us, and a swim and kayak were in order.  :)

Thursday, 9 July 2015

Floor Sheathing

Last time I left off with the problem of my t&g plywood not lining up with my joists... my solution: buy full 48" sheets of 3/4" plywood.

Dad came down one last time before his cataract surgery.  After tomorrow, he'll have to stay away from sawdust and other irritants for a couple months, so thought I'd get one more day of advice/work out of him before he's out of commission.  :)

 Getting creative when it comes to moving plywood.  It was Dad's idea!

 Working from the far end.  We cut the holes for the plumbing drains, and screwed the plywood down with flooring screws.
 Floor sheathing done!  Woo!  Feels good to have all that insulation protected.

Me and my dad. Couldn't have done any of this without him.  And I'm lucky to have a dad that didn't treat me any differently because I was a girl... it's because of him I had the confidence to take on this project. :) 

Sunday, 28 June 2015

Floor Insulation

Had a great day adding insulation to the floor.  I knew this part would be tricky, but I had a great bunch of worker bees helping me!   I want the whole exterior to be wrapped in 2 inches of EPS rigid foam insulation, and that includes the underside of the floor system. 

I'm using EPS becuase of it's breathability.  It is vapour permeable so it will not trap moisture inside the walls. I specifically chose TrueFoam Foundation Plus because it is made locally, and they have many initiatives for recycling styrofoam.


 Ann helped me carry the rigid insulation to the site.  The rigid was glued to the bottom of the frame (using construction adhesive that wouldn't melt the foam) then covered with a thin layer of plywood.

Hard to see, but Rob is underneath the frame, screwing the 3/8" pressure treated plywood to the bottom of the frame (through the 2" if rigid) to protect it from critters.


 Connie snapping chalk line to cut the final piece of plywood for under the floor.

Teamwork!  We all stood on/held the plywood while Rob cut it to the proper size.


The cavities were then filled with Roxul insulation.  I couldn't get the 7-1/2" (R32) to fill the floor cavity fully, so instead I lined the bottom of each with 2" rigid insulation, then used 5-1/2" Roxul (R-22) to fill it to the top.  In the end my floor will have an R-value of about R38, which is overkill!  But made sense with the 2x8 floor construction.


Connie and Kyle measuring the 2" rigid to fill each cavity.


 
The rigid was cut small, leaving an inch around the edge.  This gap was filled with spray foam to help air seal the cavity from any air infiltration from below.

  Once dry, we trimmed the overflow of foam insulation so the Roxul would fill the cavity nicely.


Roxul in place at this end.

Roxul was lovely to work with!  You have to be gentle because it crumbles if you grab too hard, but it cuts like butter with a bread knife and filled the cavities nicely.  I chose it because it's fireproof, resistant to rot, keeps its shape over time, and retains its R-value regardless of humidity or temperature variations. 


It's easy to leave a gap along the edges (where the Roxul meets the joists) when you are patting the Roxul into place, but these gaps can reduce the effectiveness of the insulation if any cold air is allowed to infiltrate this space.  So, before covering the Roxul with the vapour barrier, we went around the edges of each batt with a putty knife, gently raising the edges to the level of the joists, eliminating any gaps.


 More construction adhesive to hold the vapour barrier in place and help with air sealing.  The less air passing through the floor, the less chance for heat loss/gain or moisture problems. 


Laying out the vapour barrier.  I wish I had rubber gaskets to seal around the drain pipes, but Tuck Tape will have to do.
 Sticking the vapour barrier down in the adhesive.

My hope was to sheathe the floor with 3/4" plywood before heading home, but unfortunately I bought tongue & groove plywood, which is 47.5" wide instead of the full 48".  Since I framed the floor with 48" centres, the plywood joins were not lining up with my joists.  With the insulation and vapour barrier in place, moving the joists or adding an extra nailing surface was not an option.  I decided to call it a day and think about a solution.


 Tools packed up and tarp in place.  See you in two weeks!


Big thanks to my worker bees!  Such a great group to work with!

Thursday, 25 June 2015

Floor Plumbing

Dad came up to help me square the floor and attach the frame to the posts using Simpson Stong-Tie brackets.



Then we cut holes for the drainage pipes for the shower and sink.   I'm using 1-1/2" ABS pipe.  Knowing where the shower drain should be was a bit tricky without actually having the shower there; hopefully I put it in the right place!






 With all the precision work done, I'm ready to move on to finishing the floor.